Swiss freeze on Russian assets dwindles to $6.36b in '23    India's business activity booms in April    China's '40 coal cutback falls short, threatens climate    World Bank pauses $150m funding for Tanzanian tourism project    European stocks reach week-high levels    China obtains banned Nvidia AI chips through resellers    Gold loses momentum on Tuesday after strong run    Amir Karara reflects on 'Beit Al-Rifai' success, aspires for future collaborations    Russia to focus on multipolar world, business dialogues with key partners at SPIEF 2024    African Hidden Champions to host soirée celebrating rising business stars    Ministers of Health, Education launch 'Partnership for Healthy Cities' initiative in schools    Egypt explores new Chinese investment opportunities for New Alamein's planned free zone    Amstone Egypt unveils groundbreaking "Hydra B5" Patrol Boat, bolstering domestic defence production    Egyptian President and Spanish PM discuss Middle East tensions, bilateral relations in phone call    Climate change risks 70% of global workforce – ILO    Health Ministry, EADP establish cooperation protocol for African initiatives    Health Ministry collaborates with ECS to boost medical tourism, global outreach    Prime Minister Madbouly reviews cooperation with South Sudan    Ramses II statue head returns to Egypt after repatriation from Switzerland    EU, G7 leaders urge de-escalation amid heightened Middle East tensions    Egypt retains top spot in CFA's MENA Research Challenge    Egyptian public, private sectors off on Apr 25 marking Sinai Liberation    EU pledges €3.5b for oceans, environment    Egypt forms supreme committee to revive historic Ahl Al-Bayt Trail    Debt swaps could unlock $100b for climate action    Acts of goodness: Transforming companies, people, communities    President Al-Sisi embarks on new term with pledge for prosperity, democratic evolution    Amal Al Ghad Magazine congratulates President Sisi on new office term    Egypt starts construction of groundwater drinking water stations in South Sudan    Egyptian, Japanese Judo communities celebrate new coach at Tokyo's Embassy in Cairo    Uppingham Cairo and Rafa Nadal Academy Unite to Elevate Sports Education in Egypt with the Introduction of the "Rafa Nadal Tennis Program"    Financial literacy becomes extremely important – EGX official    Euro area annual inflation up to 2.9% – Eurostat    BYD، Brazil's Sigma Lithium JV likely    UNESCO celebrates World Arabic Language Day    Motaz Azaiza mural in Manchester tribute to Palestinian journalists    Russia says it's in sync with US, China, Pakistan on Taliban    It's a bit frustrating to draw at home: Real Madrid keeper after Villarreal game    Shoukry reviews with Guterres Egypt's efforts to achieve SDGs, promote human rights    Sudan says countries must cooperate on vaccines    Johnson & Johnson: Second shot boosts antibodies and protection against COVID-19    Egypt to tax bloggers, YouTubers    Egypt's FM asserts importance of stability in Libya, holding elections as scheduled    We mustn't lose touch: Muller after Bayern win in Bundesliga    Egypt records 36 new deaths from Covid-19, highest since mid June    Egypt sells $3 bln US-dollar dominated eurobonds    Gamal Hanafy's ceramic exhibition at Gezira Arts Centre is a must go    Italian Institute Director Davide Scalmani presents activities of the Cairo Institute for ITALIANA.IT platform    







Thank you for reporting!
This image will be automatically disabled when it gets reported by several people.



Pyramid restoration restarts
Published in Al-Ahram Weekly on 10 - 09 - 2014

When Minister of Antiquities Mamdouh Eldamaty announced the resumption of work at Djoser's Step Pyramid in Saqqara this week, after some four years' delay, the decision was generally applauded. But some archeologists are raising concerns about the company chosen to do the restoration.
They accused the ministry of negligence in awarding the work to the Al-Shorbagi Company, which, they say, was responsible for the earlier collapse of a block of the 4,600-year-old Step Pyramid.
Amir Gamal, representative of the Non-Stop Robberies pressure group, accused the company and the ministry of not following international restoration standards because they built a new wall around the pyramid. International rules prevent such new additions being made, he said.
Gamal added that the company, hired in 2006, had not finished the work by 2008, as specified in the contract. “Meanwhile, the condition of the pyramid has been going from bad to worse,” he said.
“The company does not specialise in restoration, and it has never carried out restoration work in Egypt,” Gamal said, adding that the Al-Shorbagy Company had previously only built cafeterias and other modern buildings at archaeological sites.
“If the ministry is confident in the restoration work that is being carried out, it should release a technical report for all to see,” he added.
Ahmed Shehab, an official of the Preserving Egypt Antiquities Organisation, an NGO, said that he was concerned because a 2011 UNESCO report had said that the pyramid was at risk and there was no proper restoration plan.
“These accusations are unfounded,” said Kamal Wahid, director-general of Giza Antiquities. He added that the restoration work was being carried out according to plans approved by UNESCO, the Ministry of Antiquities and the relevant consultancy bureau.
“The Al-Shorbagy Company, in charge of the restoration, is registered with the government as an ‘A' category company, like Arab Contractors and Orascom, which means that it is qualified for the work,” Wahid said.
The company is following a plan drawn up by specialists in the field and its work is under the supervision of the ministry's consultancy bureau, led by the well-known architect Hassan Fahmy, he added. An architectural committee, including professors of architecture from Cairo and Ain Shams universities and led by Mustafa Al-Ghamrawi, is also reviewing the restoration.
Wahid said that it is not true that a wall has been built around the pyramid, or that a block of the pyramid has fallen. “All the blocks scattered around the pyramid fell away over centuries as a result of environmental stresses,” he said, adding that these blocks had been collected, cleaned, and returned to their original positions as part of the first phase of the work.
Blocks damaged beyond repair have been replaced with replicas to fill the gaps in the pyramid's structure, he said, and the whole structure has been subjected to careful tests.
“A delegation from UNESCO and ICOM [International Council of Monuments] is now visiting several sites and museums in Egypt and it will soon issue its report,” Wahid said, adding that the report will adjudicate between the claims of the ministry and its critics.
Youssef Khalifa, head of ancient Egyptian antiquities at the ministry, accused the critics of creating a false controversy that would have a negative impact on the economy and efforts to stimulate tourism.
The restoration of Djoser's Step Pyramid started in 2002, Wahid said, when he had warned the then minister of antiquities, Zahi Hawass, of the threats to the structure. Hawass appointed a team of Egyptian and foreign archaeologists who began a study of the structure with a view to comprehensive restoration, he added.
Geological surveys and laboratory tests of the ground material has been done, and an analysis of the structure carried out. In 2006, the Al-Shorbagy Company was selected, through a bidding process, to carry out the restoration work recommended in the report.
The restoration work continued until 2010, when it was suspended for budgetary reasons. Meanwhile, a British team used giant air bags in the pyramid's inner chamber to support the ceiling, which was in danger of collapse.
Following the 25 January Revolution, work was again suspended because of money problems. Last week, during Eldamaty's visit to the site, he announced that a new budget would see the work resumed for completion by 2015.
The ancient Egyptian architect Imhotep, the pyramid's builder, initially envisioned a traditional flat-roofed mastaba for the funerary complex holding the mummy of the Third Dynasty Pharaoh Djoser (2667-2648 BCE). But by the end of Djoser's 19-year reign, his tomb in the Saqqara necropolis had grown to a 62-metre-high, six-layered structure, which is essentially what can be seen at the site today.
At the time of its completion, the pyramid was the largest building ever constructed, demonstrating a sophisticated and dramatic leap in architectural size and style.
The Step Pyramid complex was originally enclosed by a limestone wall that was 10.5 metres high and 1.64 metres thick. It covered an area of 15 hectares, the size of a large town in the third millennium BCE. Inside the walls was a huge complex of ceremonial and administrative buildings, including north and south pavilions, underground passages and terraces, finely carved façades, ribbed and fluted columns, stairways, platforms, shrines, and life-sized statues.
At the centre was the Step Pyramid, built out of 330,400 cubic metres of clay, stone, reeds and wood, making the structure more durable than earlier pyramids that were built using mud bricks.
The elements of the complex at ground level are only a small part of the whole since a large part of the building works are underground, created to hide the burial chamber and discourage grave robbers. The massive underground space is almost six-km long and includes a maze of tunnels, shafts, chambers, galleries and storerooms.
Nevertheless, the burial chamber was plundered in antiquity and re-used for other burials in the Late Period. All that now remains of Djoser is his mummified left foot.
One of the most striking parts of the complex is the eastern chamber, thought to be the pharaoh's palace in the afterlife. Here craftsmen produced exquisite decorations using faience and limestone, with rows of blue faience tiles with raised bands of limestone simulating a reed-mat structure.
The decoration was originally arranged into six panels, the three on the north side topped with an arch supported by a simulated pillar. One of the panels contained the real doorway with a limestone frame bearing the name and title of Djoser. The three southern panels framed false-door stelae showing Djoser performing ritual visits to various shrines. This chamber was never completed, however. The builders left the east wall unfinished, roughly hacked out of the rock, and the decorators seem to have left in a hurry.
All four walls of two further chambers were originally covered with the same inlay of blue tile and the doorways framed with the name of Djoser-ti, Djoser's successor. These would have represented the inner private rooms of the palace.
To the north of the pyramid stands the mortuary temple, now in ruins, though its southern wall still bears a carved cobra-head frieze. The south wall is connected from the outside to the southern tomb by a stairway with a large hole on the left side. At the bottom of this hole is an entrance leading to a set of chambers lined with blue tiles similar to those in the pyramid's burial chamber. The inscriptions in these chambers are perfectly executed and exactly in line.
The Step Pyramid complex stood untouched until the 17th century when European travellers attempted to explore the underground chambers. At the turn of the 19th century, research inside the pyramid began when the Prussian explorer Johann Heinrich Freiherr von Minutoli discovered the access tunnel that runs under the pyramid from the north.
In 1837 the British researcher John Perring found the underground galleries beneath the main structure. Soon afterwards a Prussian expedition led by Karl Lepsius carried out more excavations on the pyramid's side.
However, systematic research on the Djoser complex was first conducted only in the 1920s by the British archaeologist Cecil Firth. He was soon joined by the French architect Jean-Philippe Lauer, who made the excavation of the complex his life's work.
Regretfully, the sands of time have taken their toll on the Step Pyramid. Most of the outer casing is gone, the core of the masonry has disappeared in some places, and deep cracks have spread over the walls and ceilings of the pyramid's underground corridors, while several parts of the queen's tunnels, found beneath the pyramid's main shaft, have collapsed.
For safety reasons, the pyramid is closed to visitors.
Various projects were proposed to save the monument, but it was only in 2003 that the then Supreme Council of Antiquities gave the go-ahead for the restoration work. The aim today is for work at the site to be completed by 2015 and for the area to be developed for tourism.