Egypt's ICT sector a government priority, creating 70,000 new jobs, says PM    Egypt's SCZONE, China discuss boosting investment in auto, clean energy sectors    Tensions escalate in Gaza as Israeli violations persist, humanitarian crisis deepens    Egypt, India explore cooperation in high-tech pharmaceutical manufacturing, health investments    Egypt, World Bank explore expanded cooperation on infrastructure, energy, water    Egypt, Sudan, UN convene to ramp up humanitarian aid in Sudan    Egypt, China's Jiangsu Fenghai discuss joint seawater desalination projects    Egypt's FRA issues first-ever rules for reinsurers to boost market oversight    LLC vs Sole Establishment in Dubai: Which is right for you?    French court grants early release to former President Nicolas Sarkozy    Egypt releases 2023 State of Environment Report    Egyptians vote in 1st stage of lower house of parliament elections    Egypt's Al-Sisi, Russian security chief discuss Gaza, Ukraine and bilateral ties    Grand Egyptian Museum welcomes over 12,000 visitors on seventh day    Egypt's private medical insurance tops EGP 13b amid regulatory reforms – EHA chair    400 children with disabilities take part in 'Their Right to Joy' marathon    Egypt repatriates 36 smuggled ancient artefacts from the US    Grand Egyptian Museum attracts 18k visitors on first public opening day    'Royalty on the Nile': Grand Ball of Monte-Carlo comes to Cairo    Egypt, Albania discuss expanding healthcare cooperation    VS-FILM Festival for Very Short Films Ignites El Sokhna    Egypt's cultural palaces authority launches nationwide arts and culture events    Egypt launches Red Sea Open to boost tourism, international profile    Qatar to activate Egypt investment package with Matrouh deal in days: Cabinet    Hungary, Egypt strengthen ties as Orbán anticipates Sisi's 2026 visit    Omar Hisham Talaat: Media partnership with 'On Sports' key to promoting Egyptian golf tourism    Egypt establishes high-level committee, insurance fund to address medical errors    Sisi expands national support fund to include diplomats who died on duty    Madinaty Golf Club to host 104th Egyptian Open    Egypt's PM reviews efforts to remove Nile River encroachments    Al-Sisi: Cairo to host Gaza reconstruction conference in November    Egypt will never relinquish historical Nile water rights, PM says    Al-Sisi, Burhan discuss efforts to end Sudan war, address Nile Dam dispute in Cairo talks    Egypt resolves dispute between top African sports bodies ahead of 2027 African Games    Germany among EU's priciest labour markets – official data    Paris Olympic gold '24 medals hit record value    It's a bit frustrating to draw at home: Real Madrid keeper after Villarreal game    Russia says it's in sync with US, China, Pakistan on Taliban    Shoukry reviews with Guterres Egypt's efforts to achieve SDGs, promote human rights    Sudan says countries must cooperate on vaccines    Johnson & Johnson: Second shot boosts antibodies and protection against COVID-19    Egypt to tax bloggers, YouTubers    Egypt's FM asserts importance of stability in Libya, holding elections as scheduled    We mustn't lose touch: Muller after Bayern win in Bundesliga    Egypt records 36 new deaths from Covid-19, highest since mid June    Egypt sells $3 bln US-dollar dominated eurobonds    Gamal Hanafy's ceramic exhibition at Gezira Arts Centre is a must go    Italian Institute Director Davide Scalmani presents activities of the Cairo Institute for ITALIANA.IT platform    







Thank you for reporting!
This image will be automatically disabled when it gets reported by several people.



Unknowns about the Renaissance Dam
Published in Al-Ahram Weekly on 12 - 03 - 2014

Ethiopia's Renaissance Dam project had long been a subject of tension between Cairo and Addis Ababa. The tensions began to flare on 2 April 2011 — shortly after Egypt's 25 January Revolution — when the latter announced that it had laid the cornerstones to the dam and, subsequently, when it began to divert the Blue Nile in order to construct the dam.

At that time, then Egyptian prime minister Essam Sharaf and his Ethiopian counterpart Meles Zenawi agreed to create a tripartite technical committee tasked with studying the designs, statistics and other information provided by Ethiopia on that dam, the specifications for which were particularly alarming to Egypt. Originally envisaged to have a reservoir capacity of 14 billion cubic metres, the designs for project steadily grew in their ambitions and now provide for a 74 billion cubic metre reservoir capacity.

The technical committee set to work and completed its report in May 2013. Although the three parties in this committee (Egypt, Sudan and Ethiopia) agreed not to publicise the report, various agencies have disclosed its most important substance. The following is some observations on that substance.

A chief finding of the committee, after studying the facts and information supplied by Ethiopia regarding the safety of the dam in light of the nature of the soil on which it is to be constructed and the potential impact of the heavy vertical and horizontal fracturing in the bedrock, was that geophysical properties were not taken sufficiently into account in the calculations for both the main dam (the Renaissance Dam), to be constructed of reinforced concrete, and the saddle dam, to be constructed of stone and rubble.

In addition, according to the summary of the information in the tripartite technical committee's report, the planners had not studied the potential effect of a dam of such a huge reservoir capacity (74 billion cubic metres) as a source for generating a subterranean reservoir below the lakes area and the potential impact of this on the properties of the sedimentary and metamorphic rock beneath the dam. Such factors could lead to seepage beneath the dams and heighten the likelihood of slippage and the consequent partial or total collapse of a dam of such excessive specifications as the Renaissance Dam.

It is also important to note that no studies, designs or data have been made available on the saddle dam. Therefore, experts have no information on which to base assessments regarding its ability to withstand the pressure of the water that accumulates in its reservoir (63 billion cubic metres at the rate of 500 cubic metres per second). It should also be borne in mind that this water will be laden with sediments of various types and sizes and there is little knowledge as to how the dam can tolerate the physical impact of the rush and weight of the sediment-laden water during the succession of rainy seasons that will pass during the projected life expectancy of the dam.

Nor were studies conducted on the geo-chemical impacts on the bedrock as the result of the development of a subterranean reserve beneath the dam's reservoir area. That much of that rock is volcanic and, therefore, very vulnerable to chemical reaction processes, increases the likelihood of changes in the mechanical properties of the rocks and sediment both in the reservoir area as well as beneath the dam itself, which could result in fracturing or weakening its cohesion and, hence, possible ground sinkage.

There is not also sufficient information on the anticipated environmental impact of the construction of the dam and reservoir. Nor has sufficient study been accorded to the chemical properties of the water that will be stored behind the dam or that will pass through its sluices, and the impact of this chemical composition on river life.

In like manner, no study has been made of how the water that gushes from the dam's turbines will effect the geo-morphological properties of the Blue Nile in Sudan and of the impact of this on agricultural land and facilities, the foundations of buildings and bridges, and the dams and islands that the river traverses on its way to Khartoum.

To further underscore the huge gap or even total absence in geological and geo-technical information related to Ethiopia's Renaissance Dam project, whether due to the lack of studies or because relevant information has been deliberately withheld from the tripartite technical committee, little or no attention has been accorded to studying the seismological dimensions of the geo-technological feasibility of the dam.

The writer is former president of Menoufiya University and an expert on water issues.


Clic here to read the story from its source.