STOXX 600 inches Up, tech wins over banking woes    Egypt's gold prices slightly down on Wednesday    Tesla to incur $350m in layoff expenses in Q2    GAFI empowers entrepreneurs, startups in collaboration with African Development Bank    Egyptian exporters advocate for two-year tax exemption    Egyptian Prime Minister follows up on efforts to increase strategic reserves of essential commodities    Italy hits Amazon with a €10m fine over anti-competitive practices    Environment Ministry, Haretna Foundation sign protocol for sustainable development    After 200 days of war, our resolve stands unyielding, akin to might of mountains: Abu Ubaida    World Bank pauses $150m funding for Tanzanian tourism project    China's '40 coal cutback falls short, threatens climate    Swiss freeze on Russian assets dwindles to $6.36b in '23    Amir Karara reflects on 'Beit Al-Rifai' success, aspires for future collaborations    Ministers of Health, Education launch 'Partnership for Healthy Cities' initiative in schools    Egyptian President and Spanish PM discuss Middle East tensions, bilateral relations in phone call    Amstone Egypt unveils groundbreaking "Hydra B5" Patrol Boat, bolstering domestic defence production    Climate change risks 70% of global workforce – ILO    Health Ministry, EADP establish cooperation protocol for African initiatives    Prime Minister Madbouly reviews cooperation with South Sudan    Ramses II statue head returns to Egypt after repatriation from Switzerland    Egypt retains top spot in CFA's MENA Research Challenge    Egyptian public, private sectors off on Apr 25 marking Sinai Liberation    EU pledges €3.5b for oceans, environment    Egypt forms supreme committee to revive historic Ahl Al-Bayt Trail    Debt swaps could unlock $100b for climate action    Acts of goodness: Transforming companies, people, communities    President Al-Sisi embarks on new term with pledge for prosperity, democratic evolution    Amal Al Ghad Magazine congratulates President Sisi on new office term    Egypt starts construction of groundwater drinking water stations in South Sudan    Egyptian, Japanese Judo communities celebrate new coach at Tokyo's Embassy in Cairo    Uppingham Cairo and Rafa Nadal Academy Unite to Elevate Sports Education in Egypt with the Introduction of the "Rafa Nadal Tennis Program"    Financial literacy becomes extremely important – EGX official    Euro area annual inflation up to 2.9% – Eurostat    BYD، Brazil's Sigma Lithium JV likely    UNESCO celebrates World Arabic Language Day    Motaz Azaiza mural in Manchester tribute to Palestinian journalists    Russia says it's in sync with US, China, Pakistan on Taliban    It's a bit frustrating to draw at home: Real Madrid keeper after Villarreal game    Shoukry reviews with Guterres Egypt's efforts to achieve SDGs, promote human rights    Sudan says countries must cooperate on vaccines    Johnson & Johnson: Second shot boosts antibodies and protection against COVID-19    Egypt to tax bloggers, YouTubers    Egypt's FM asserts importance of stability in Libya, holding elections as scheduled    We mustn't lose touch: Muller after Bayern win in Bundesliga    Egypt records 36 new deaths from Covid-19, highest since mid June    Egypt sells $3 bln US-dollar dominated eurobonds    Gamal Hanafy's ceramic exhibition at Gezira Arts Centre is a must go    Italian Institute Director Davide Scalmani presents activities of the Cairo Institute for ITALIANA.IT platform    







Thank you for reporting!
This image will be automatically disabled when it gets reported by several people.



Ethiopia expects Nile dam to be ready to start operation in late 2020
Published in Ahram Online on 03 - 01 - 2019

Ethiopia's $4 billion dam project on the River Nile, which has been beset by construction delays and criticism from Egypt, will start initial operations in December 2020, the water and energy minister said on Thursday.
The planned 6,000-megawatt Grand Renaissance Dam is the centrepiece of Ethiopia's bid to become Africa's biggest power exporter, but until this week progress had been unclear after Prime Minister Abiy Ahmed last August cancelled a state-run conglomerate's contract to build the turbines.
State media reported on Wednesday that the government had signed an agreement with GE Hydro France, a unit of GE Renewables, to accelerate the completion of the dam, and water and energy minister Seleshi Bekele said on Thursday the project was on track to open in two years' time.
"750 megawatts is the planned initial production with two turbines," Seleshi told parliament. The government expected the dam to be fully operational by the end of 2022, he said.
The project has caused problems with Egypt, which fears the dam will restrict Nile River waters coming down from Ethiopia's highlands, through the deserts of Sudan, to Egyptian fields and reservoirs.
Ethiopia disputes that and in November Abiy was quoted by Egyptian state media as saying he wanted to preserve Egypt's Nile rights.
When Abiy cancelled the contract of Ethiopian military conglomerate Metals and Engineering Corporation (METEC) in August, he said not a single turbine was operational more than seven years after the government awarded the contract. Dozens of senior officials from METEC, including its head, have been arrested in a corruption crackdown launched by the reformist leader who took office last year.
METEC had only completed 23 percent of the work, Seleshi said on Thursday.
There have been other construction delays.
"Purchased generators, turbines and other equipment are scattered in ports and other places, meaning more costs," Seleshi said.
GE Hydro France will be paid nearly 54 million euros ($61 million) to manufacture, fix and test turbine generators, state media said.