Al-Sisi, Emir of Kuwait discuss bilateral ties, Gaza takes centre stage    Egypt facilitates ceasefire talks between Hamas, Israel    Egypt's Al-Sisi urges unity at African Development Summit    IFZA: 2k Egyptian firms join UAE market in 3 yrs    CBE receives offers worth $1.117bn for USD-denominated T-bill auction    Mexico's economy expands by 0.2% in Q1    UAE, Iran rare economic commission set to convene in Abu Dhabi    EU funds body backs capital market union plan    KOICA, Plan International mark conclusion of Humanitarian Partnership Programme in Egypt    Microsoft to invest $1.7b in Indonesia's cloud, AI infrastructure    Egyptian, Bosnian leaders vow closer ties during high-level meeting in Cairo    S. Africa regards BHP bid typical market activity    Sweilam highlights Egypt's water needs, cooperation efforts during Baghdad Conference    AstraZeneca, Ministry of Health launch early detection and treatment campaign against liver cancer    AstraZeneca injects $50m in Egypt over four years    Egypt, AstraZeneca sign liver cancer MoU    Negativity about vaccination on Twitter increases after COVID-19 vaccines become available    Environment Ministry, Haretna Foundation sign protocol for sustainable development    Swiss freeze on Russian assets dwindles to $6.36b in '23    Amir Karara reflects on 'Beit Al-Rifai' success, aspires for future collaborations    Climate change risks 70% of global workforce – ILO    Prime Minister Madbouly reviews cooperation with South Sudan    Ramses II statue head returns to Egypt after repatriation from Switzerland    Egypt retains top spot in CFA's MENA Research Challenge    Egyptian public, private sectors off on Apr 25 marking Sinai Liberation    Egypt forms supreme committee to revive historic Ahl Al-Bayt Trail    Debt swaps could unlock $100b for climate action    President Al-Sisi embarks on new term with pledge for prosperity, democratic evolution    Amal Al Ghad Magazine congratulates President Sisi on new office term    Egyptian, Japanese Judo communities celebrate new coach at Tokyo's Embassy in Cairo    Uppingham Cairo and Rafa Nadal Academy Unite to Elevate Sports Education in Egypt with the Introduction of the "Rafa Nadal Tennis Program"    Financial literacy becomes extremely important – EGX official    Euro area annual inflation up to 2.9% – Eurostat    BYD، Brazil's Sigma Lithium JV likely    UNESCO celebrates World Arabic Language Day    Motaz Azaiza mural in Manchester tribute to Palestinian journalists    Russia says it's in sync with US, China, Pakistan on Taliban    It's a bit frustrating to draw at home: Real Madrid keeper after Villarreal game    Shoukry reviews with Guterres Egypt's efforts to achieve SDGs, promote human rights    Sudan says countries must cooperate on vaccines    Johnson & Johnson: Second shot boosts antibodies and protection against COVID-19    Egypt to tax bloggers, YouTubers    Egypt's FM asserts importance of stability in Libya, holding elections as scheduled    We mustn't lose touch: Muller after Bayern win in Bundesliga    Egypt records 36 new deaths from Covid-19, highest since mid June    Egypt sells $3 bln US-dollar dominated eurobonds    Gamal Hanafy's ceramic exhibition at Gezira Arts Centre is a must go    Italian Institute Director Davide Scalmani presents activities of the Cairo Institute for ITALIANA.IT platform    







Thank you for reporting!
This image will be automatically disabled when it gets reported by several people.



Investments in FiT projects amount to $350m
Company aims to produce 130 MW from FiT
Published in Daily News Egypt on 07 - 11 - 2017

Infinity Solar, a subsidiary of Mansour Group, owned by businessman Mohamed Mansour, has completed establishment of the first solar power plant in Benban, Aswan as part of the Feed-in Tariff (FiT) program, which was launched by the government in 2014. The company links its projects to the national electricity grid and sells production to the Egyptian Electricity Transmission Company (EETC) at 14.3 cents per kW.
Daily News Egypt met with the board of directors of the company to discuss solar energy projects being implemented in Egypt and explore their views of the FiT projects, along with their future plans in renewable energy sector.
How did the company implement the first solar plant?
The company's financial division manager Mohamed Shehata said that the company completed the implementation of a solar power plant with capacity of 50 MW in Benban, Aswan, but 62 MW solar cells have been installed, due to the presence of cracks in the ground. The station was implemented in cooperation with the German company IB Vogt, which contributed 48% of the project.
Infinity arranged 85% of the funding through PLb bank in Germany and agreed with the Arab African International Bank to finance the local part of the project.
Investment manager at the company Taymor Aboul Kheir said that the return on investments of the solar power plant in the first phase of the FiT projects amounts to 12-14%.
According to the terms and conditions of the first phase of the FiT, EETC will buy electricity produced from solar plants at 14.3 cents per kW for 25 years.
What challenges did the company face during implementation?
HR and administrative director at Infinity for Solar Systems Hesham El Gamal said that the company has been working on a very fast pace over the past few months on two shifts. The company has used generators to power the site in the dark and overcome the challenging hot weather in Benban.
He added that the company will start the experimental operation during the current week and will link the production capacity of the station to the national electricity network within two weeks, in coordination with the EETC and XDEgymac to transfer the power from the project through the transformers substations.
What are the projects that you intend to implement in the second phase of the FiT?
Taymor Aboul Kheir said that the company has projects with a capacity of 130 MW and has completed financial closure in the time set by the Ministry of Electricity.
He added that the company has a project in the first phase working with El Mansour & El Maghraby alliance on a project of 30 MW, which was then postponed to the second phase since the company was unable to access the funding for the project based on the conditions set by the Ministry of Electricity, which includes local arbitration in Egypt in case of conflict, which was refused by the companies.
He explained that the European Bank for Reconstruction and Development (EBRD) told them that the capacity of the project is low and should be increased to finance the project in the second phase of the FiT. Infinity has acquired TAQA Solar project of 50 MW and funding from EBRD then cover some 80 MW.
He noted that Infinity Solar acquired 42% stake in the 50 MW Phoenix Power Company project, which is funded by the International Finance Corporation (IFC).
Mohamed Shehata, financial division manager (Photo by Ahmed Hendawy)
What is the strategy of the company in the coming period?
Taymor Aboul Kheir said that the company aims to expand in solar energy projects in the coming period, where it is awaiting the approval of the financial model of the projects in the second phase to begin constructions – which is similar to the strategy adopted in the first phase. The implementation period should not take longer than six months.
He stressed that Infinity invests in long-term plan, where it intends to participate in all projects put forward by the government during the coming period. The company is always looking for opportunities in the renewable energy sector to pump more investments. The company's investments amount to $350m.
It has also submitted bids for tenders in Africa to launch solar power stations, and is considering participating in projects in Arab countries, and aims to compete in the tender for the construction of wind power plant in Greece.
What is the legal position to acquire companies?
General Counsel Hani Zahran said that the company aimed to benefit from the regulations and laws according to their desire to contribute to the projects, which include a minimum of 25% share of the alliance leader.
He said that shares owned by people in El Mansour & El Maghraby project have been restructured, based on the requirements of foreign banks financing the project. Shares owned by the personalities of the aggregate entity have been transferred to an entity in the Netherlands. This entity owns a controlling share and retains about 25% of El Mansour & El Maghraby share.
As for TAQA Solar; the alliance leader was changed as per law. The change requires submitting the paperwork again to obtain the approval. This includes the financial solvency to implement the projects. The main leader was swapped by Infinity. This was approved by the concerned bodies.

How did the decision to float the pound impact the projects?
All Infinity officials agreed that the decision taken by the state to float the pound is the best, encouraging foreign companies to invest in Egypt and eliminating the constant concerns and questions about how to find the dollar and how to repatriate instalments and profits to financiers.
Taymor Aboul Kheir said that the German bank funding the company in the first phase of the FiT told them that it is necessary to provide a dollar reserve to guarantee the payment of loan instalments. The liberalization of the exchange rate contributed to encouraging investment and attracting new capital.
The company's financial division manager Mohamed Shehata said that the impact of the decision to float the pound on solar projects is not very large and limited, despite the increase in the budget allocated to projects. The company has calculated the cost of its equipment in dollars and financing in foreign currency, except for the local part used to pay the customs and companies engaged in civil works.
How will the employment of solar energy projects be determined?
HR and administrative director at Infinity for Solar Systems Hesham El Gamal said that funding bodies required hiring a company to manage project services in Benban, Aswan, including establishing walls, employment, and recruitment.
He explained that the Benban project services management task was granted to Hassan Allam, which will establish a training centre in cooperation with residents of Benban. They met with Aswan Governor and agreed to form a committee to oversee the projects and employ a number of Aswan villages' residents in the FiT projects that will create some 15,000 jobs.
Company officials said that the wind farm projects in the second phase of the FiT need reconsideration to match the success of the solar plants, where Infinity, like all companies, is suffering from time constraints and low purchase price.


Clic here to read the story from its source.